Société Egyptienne D’entreprises

Potable Water :

pressurized pipelines from 2 nd. Extension of Embaba potable water purification plant (2 nd. Satge) to supply water for Giza Northern Villages

Project value & Date:

  • The Value of contract is 204.772297 Million EGP
  • The Contract Date 9/21/2010
  • The End Date 12/31/2023

Project Description:

**Potable Water networks:
* D.I pipelines of 600 : 1000 mm dia., & 42.677 km total length.
* HDPE pipelines of 110 : 600 mm dia. & 38.41 km total length.
*73nos. R.C valve chambers.
* 6 nos. Elevated Tanks + service buildings.
** Crossings:
* 14 nos. over canals & drains for D.I pipelines of 400 : 1000 mm dia. 
* 6 nos. pipe jacking system under railways, canals & drains of 400 : 1000 mm dia. & total length 210 m. 