Société Egyptienne D’entreprises

Potable Water :

Design and execution of the Extension of purification plant in El Obour City with additional capacity of 400000 m3/day)

Project value & Date:

  • The Value of contract is 277.223758 Million EGP
  • The Contract Date 10/28/2008
  • The End Date 2/28/2017

Project Description:

(A) Completion of new units in existing plant
- 3 nos. condenser buildings for concentrated basins of 22 m dia.
- 2 nos. sludge collector building.
- 1 nos. sludge compression building.
(B) Extension works:
- Main distribution well.
- Subsidiary distribution well.
- 2 nos Clarifires .
- 2 nos. Filters.
- 2 nos. Ground Tanks 20000 m3 for each one
- Chlorine & chemicals buildings.
- Drying basins.
- Balance Tank & Irrigation pump station.
- Diesel building.
- Transformer building.
- Sludge pump.
- Returning pump station.
- Condenser (for 3 units).
- Sludge pumps.
- Fence & safety room.
- Landscape.
- Sludge drainage chamber & wastewater network manholes.
- Connection Pipelines:
Inlet steel pipeline of 1800 mm dia.
Outlet steel pipeline of 1600 mm dia. 