Société Egyptienne D’entreprises

Roads, Bridges, Land Reclamation and Irrigation :

Execution of first stage irrigation networks to drain on third wastewater in Sadat City

Project value & Date:

  • The Value of contract is 28.773522 Million EGP
  • The Contract Date 2/24/2016
  • The End Date 6/30/2024

Project Description:

* Irrigation Networks using GRP pipelines 500 : 800 mm dia.& UPVC pipelines 250 mm dia. 