Project Description:
1.Design and implementation of a line of steel pipes length 225 km diameters ranging from 1200 mm to 1600 mm.
2.Flexible floss tubes with length of 12.8 km diameter 400 mm.
3.Design and implementation of reinforced or prestressed concrete tanks with a capacity of not less than 350,000 m3 production tanks and 93,000 m3 distribution tanks.
4.Design and implementation of (4) new pumping stations.
5.Design and construction of chlorine building and equipment at Sohar Reservoir site.
6.Design and implementation of the automatic control system to connect with the existing Escada system and design and implementation of the new Escada system.